Unit 6


The building of unit number 6 was started end of May 2005. This house completed Building Phase II, namely having 6 specially designed houses up and running. Unit number 6 was finished half of July 2005.


House number 6 finished and completes the building phase II: 15th of July 2005

 

Almost finished: 28 June 2005


Walls established up to roof height: date 6th of June 2005


Concrete slab being poured: 3rd of June 2005


Walls put in place on top of the foundations: 30th of May 2005


Foundations being poured: 26th of May 2005